Nucor Steel Mill

Nucor Steel Mill
Project : Nucor Steel Mill
Client : Decatur, AL

Scope of Work:

This project included the design and implementation of the new T5, 200 MVA, 500 – 34.5 kV Power Transformer. Scope of work included the substation expansions and all mechanical, civil and structural scope of engineering.

The 500 kV structures included tapered tubular design of the steel and the installation of a new 500 kV Gas Circuit Breaker as well as new 500 kV Disconnect Switches. Secondary design included the design for 3000 amp rated bus configuration.

Dates: Engineering, 2012; Construction, 2013.